See below for building-specific reminders to consider in case of utility shutdown requests:
Electrical shutdown will shut down alarm for vault. May need added security and may trigger alarm when re-energized.
Freezers have backup chilled water connection that can be utilized.
Freezers have backup chilled water connection that can be utilized.
Artwork needs specific humidity/temperature ranges. Shutdown of Steam/Chilled water or Electricity may affect this. Backup systems may be needed depending on shutdown length.
Artwork needs specific humidity/temperature ranges. Shutdown of Steam/Chilled water or Electricity may affect this. Backup systems may be needed depending on shutdown length.
Electrical shutdown will impact seismograph. Backup generator may be needed.
Electrical is fed from #027/Eastburn.
Steam is fed from #016/Communication.
This building houses Distance Learning and TV data networks. Cooling or Electrical shutdowns may affect these components.
Schedule shutdowns around research projects. Backup Generator might not cover all deep freezers.
Electrical shutdown will turn off fish tank components. Backup may be needed. Electrical feeds #021B/Biological Sciences Annex, so the backup generator at #021B should kick on automatically.
Trailer is fed from a switch in the basement.
North Campus Steam, Chilled Water and Electrical are distributed from here.
Electrical shutdown will take bathroom water pumps offline.
There are multiple water, steam, and electrical feeds to this building. HVAC piping in phase 3 is shared with the fire system.
This building has a backup generator and standalone chiller.
Electrical PME is at NE corner of the Fieldhouse. Chilled Water shutdown will also shut down #30A/B (Dining Services/Student Services).
Admissions is run out of this building. Contact 3-0922 for shutdown coordination.
This building has a standalone chiller.
This building has a backup gas water heater for use during Steam shutdowns.
This building has a backup gas water heater for Steam shutdowns.
Same procedure as other steam systems. Verify HHW pressures, steam pressure, pump operation, and condensate receiver operation; check isolation valves (manual and BAS) and water makeup; slowly bring up by hand. Check for leaks and verify proper operation once setpoint has been reached.
Main electrical feed comes into the laundry room. Water service line to Building D has not been found.
This building has a backup generator and backup chiller.
Coordinate all shutdowns with Shelly Jones to discuss any impacts to BSL 3 area. This building has a backup generator.
PME has an auto transfer switch.
Note: This is not an NAU-maintained building. Electrical is fed out of #058/HCCC PME.
This is an American Campus Communities facility.
South Campus HTHW, Chilled Water, and Electrical is fed from here.
Renewable Energy Test Facility Solar/Wind research may back feed into this building.
Water is fed from two directions.
This is an American Campus Communities facility.
The west half of Forestry is operated by USFS.
Prolonged Heating or Electrical shutdowns will affect pool temperatures. Backup Boiler has been connected in past upstream of control valves.
Work done in service drive NW of building will suck in vehicle fumes. Schedule shutdowns around research projects.
Human Resources side is alarmed. Electrical shutdown can set off the alarm. HVAC main controller is on Human Resources side. Access needs to be coordinated with them.
Electrical junction box on NE corner of #019/Physical Sciences for connection to NAU system if purchased.