Beautifying NAU: Parking lot and street repairs this summer

Throughout the summer, construction will take place across different locations on campus to improve the condition of streets, parking lots and garages in preparation to welcome back the Lumberjack community this fall. These repairs mean that there will be partial closures of parking lots and garages, with alternative parking locations available, on designated dates. Delays in street traffic are expected as construction segments will be reduced to single-lane use.  

Street repairs  

All street repairs are scheduled to occur June 5-14.  

Repairs will begin at the intersection of Pine Knoll Drive and San Francisco Street moving west on south campus to intersect with McConnell Drive. Repairs will then move north on San Francisco Street to intersect with University Drive. 

These repairs will consist of the laying of Mastic, a trowel grade crack filler designed for repairs in asphalt and concrete. As of now, there are no full street closures scheduled or anticipated. Do plan accordingly to manage traffic delays because of one-lane traffic during the above dates.   

Parking garage repairs 

Work is scheduled to begin June 12 and expected to conclude by the end of July on San Francisco, Mountain View and Knoles garages.  

Due to scheduled events on campus, work on San Francisco garage WILL NOT take place during the month of June. Please expect maintenance and repair activities at Mountain View and Knoles Parking Garages during this time. 

Parking lot repairs 

Parking lot repairs will begin near the finalizing of street repairs on June 9 and continue through July 19. 

These repairs will be more intensive, consisting of pothole repairs, demo, pavement and concrete replacement, milling and more. Partial lot closures will take place on scheduled repair days. Alternative parking locations will be available on scheduled striping days.  

Parking lot repair schedule 

  • June 9 – Lot P1B – Partial lot closure 
  • June 12 – Lot P32B – Partial lot closure 
  • June 14 – P62A – Partial Lot Closure 
  • June 15 – P16A-P69 – Partial Lot Closure 
  • June 16-19 – P66 – Partial Lot Closure 
  • June 20 – P66-P69 – Partial Lot Closure 
  • June 21 – P69 – Partial Lot Closure 
  • June 22 – DuBois North – Partial Lot Closure 
  • June 23 – DuBois North-P64 – Partial Lot Closure 
  • June 26 – P33-DuBois North – Partial Lot Closure 
  • June 27 – DuBois North-P16A – Partial Lot Closure 
  • June 28 – 16A-P13 – Partial Lot Closure 
  • June 29-30 – P13 – Partial Lot Closure 
  • July 5 – P1A – Partial Lot Closure 
  • July 6 – P1A-P1C – Partial Lot Closure 
  • July 7, 10-11 – P1C – Partial Lot Closure 
  • July 12-13 – P62A-P64 – Partial Lot Closure*  
  • July 14 – P62A – Partial Lot Closure* 
  • July 17 – P64 – Partial Lot Closure* 
  • July 18 – P62A – Partial Lot Closure* 
  • July 19 – P64 – Partial Lot Closure* 

* P62A-P64 both to remain partially closed continuously July 12-19 

Striping schedule (with alternative parking locations):

DATE  LOT #  ALTERNATE PARKING 
JUNE 5  HLC ADA partial  P7A HLC 
  P12  P11, P19, P10 
     
JUNE 6  P5  Dupont, 2B 
  P2  P1b, P6 
     
JUNE 7  P19  P11, P12 
  P10  P11, P12, P9 
     
JUNE 8  P27 ADA partial  P31, P33, 16a 
  P7a  P1b, P6, P19 
     
JUNE 12  P11  P12, P6, P19 
  P16  P16a, P8, P9, P13 
  P17        P16a, P8, P9, P13  
     
JUNE 13  P7  HLC ADA 
  P4  P5, Knoles, P3  
     
JUNE 14  P3         P8, P13a, Knoles  
  Dupont  P3, P5 
  P1b  P2, P1C 
     
JUNE 15  P28E  P19 
  P13c  P13, P13a, 13d 
     
JUNE 20  P28 partial  P28 
  P8  P3, P5 
     
JUNE 21  15A  P13, P13D 
  P2B  Dupont, P5 
  Humphreys  P1B, P2 
     
JUNE 26  P9  P16, P11, P12 
  P28d  P7a 
  P29b  P29 
     
JULY 3  P13a  P13 
     
JULY 5  P13 partial  P13, P13b 
     
JULY 6  P6  P7a, P1B 
     
JULY 13  P1a  P2, P1B 
  P16a  P31 
     
JULY 17  P13 partial  P13, P13b