Cochise County
Population: 132,088
Size: 6,165 sq. mi.
Median Household Income: $45,906
Cochise County is home to Fort Huachuca, which is working to support Department of Defense sustainability goals by installing renewable energy generation capacity on site. There are a few other potential solar projects, and the Red Horse project, which was wind-only in 2013, was re-permitted for wind and solar and is now under construction.
Solar Project Name | Design | Megawatts | Stage of Development | Developer | Purchaser of electricity |
---|---|---|---|---|---|
Fort Huachuca | PV | 17.2 | Operating |
| Fort Huachuca |
Fort Huachuca | PV | 5 | Under Construction |
| Fort Huachuca |
Red Horse Wind/Solar I | PV | 41 | Under Construction |
| UniSource Energy |
Red Horse Solar II | PV | 20 | Under Development |
| UniSource Energy |
San Simon | PV | 1.2 | Under Development | Sulphur Springs Valley Electric Cooperative |
|
Total Under Development | 21.2 |
|
|
|
|
Total Under Construction or Operating | 63.2 |
Wind Project Name | Megawatts | Stage of Development | Developer | Purchaser of electricity |
---|---|---|---|---|
Fort Huachuca | 1 | Operating | US Army | Fort Huachuca |
Red Horse 2 Wind | 30 | Under Construction | Red Horse 2, LLC and Torch Renewable Energy, LLC | TEP |
Total Under Development | 0 |
|
|
|
Total Under Construction or Operating | 31 |